Audit a project-foundation record
A coordinator records the outcome and date but omits the sponsor, affected users, constraints, reason for the approach, and review trigger. Which repairs are necessary? Select all that apply.
Foundation audit
A date and outcome are not a complete project foundation
- OutcomeRecordedThe requested result and date are visible.
- ContextIncompletePeople, constraints, assumptions, and uncertainty are missing.
- ApproachUnsupportedNo evidence-based reason explains the delivery choice.
- ControlUnassignedAuthority and review triggers are not named.
Repair standardComplete missing evidence and seek authorization; never manufacture certainty.
Audit for missing context, unsupported approach choices, and absent control evidence before work begins.