Audit a project brief before planning

Which findings require correction before a brief becomes the planning basis? Select all that apply.

Project brief canvas

Connect a real problem to authorized success evidence

  1. ProblemCurrent gapEvidence, affected people, and information cutoff.
  2. OutcomeIntended changeValue and completion boundary, not only an output.
  3. RequirementsTestable needsCriteria, assumptions, constraints, and exclusions.
  4. SuccessEvidence + ownerMeasure, review point, and accountable authority.
Authorization gateDetailed planning starts from the approved version, not an informal promise.

A useful brief traces the current gap through affected users and testable requirements to a bounded decision.

Choose all that apply