Calculate capstone risk exposure
A capstone risk has a 30% probability and a supplied simplified impact of 12,000 USD. What is the simple expected exposure in USD?
Capstone control room
Trace the project from authorized request to accountable handoff
- FrameBrief + authorityOutcome, users, requirements, boundaries, and success.
- PlanWork + rolesSchedule, capacity, communication, RAID, and quality.
- ControlStatus + changeActuals, variance, forecast, options, and decisions.
- HandoffAccept + transitionEvidence, ownership, open items, lessons, and benefits.
Capstone standardEvery material claim traces to evidence or a named assumption and every decision traces to authority.
The integrated record connects why, what, how, who, when, current evidence, decisions, acceptance, and transition.