Respond to a capstone scope change

A new accessibility requirement is supplied after planning. Order the responsible response.

Capstone control room

Trace the project from authorized request to accountable handoff

  1. FrameBrief + authorityOutcome, users, requirements, boundaries, and success.
  2. PlanWork + rolesSchedule, capacity, communication, RAID, and quality.
  3. ControlStatus + changeActuals, variance, forecast, options, and decisions.
  4. HandoffAccept + transitionEvidence, ownership, open items, lessons, and benefits.
Capstone standardEvery material claim traces to evidence or a named assumption and every decision traces to authority.

The integrated record connects why, what, how, who, when, current evidence, decisions, acceptance, and transition.

Arrange in the correct order
  1. 1. Update baselines, acceptance, owners, and communications
  2. 2. Present options and obtain the authorized decision
  3. 3. Assess work, schedule, quality, risk, and specialist impacts
  4. 4. Validate the supplied requirement, source, scope, and urgency