Separate benefits from delivery

A new guide is accepted today, but reduced support demand can only be measured in 60 days. What should closeout record?

Closeout and transition path

Close temporary work without losing continuing ownership

  1. AcceptCriteria + decisionAuthorized deliverables, evidence, and exceptions.
  2. TransitionOperating ownerSupport, access, training, records, and open work.
  3. CloseDecision + archiveVersions, rationale, notifications, and locations.
  4. Follow upLessons + benefitsOwner, evidence source, review date, and limits.
Closure testEvery accepted remaining item survives closure with an owner, date, and escalation condition.

Acceptance, transition, remaining items, records, lessons, and later benefits review make closure accountable.