Communicate estimate uncertainty
A task depends on an unknown vendor response. What is the most responsible estimate update?
Deliverable breakdown map
Trace the outcome into owned, sequenced work
- OutcomeUseful changeThe result the project intends to support.
- DeliverableVerifiable resultA result with supplied acceptance evidence.
- Work packageManageable scopeOwned work that can be estimated and checked.
- DependencyPredecessor linkThe condition required before successor work proceeds.
Plan auditNo authorized deliverable is missing, unowned, or disconnected from its required predecessor.
Each planning layer should add enough detail to estimate, assign, sequence, and verify the authorized result.