Calculate simple schedule variance
A milestone was planned for day 12 and is now forecast for day 15. How many days late is the current forecast?
Evidence-based status dashboard
Compare actual evidence with the approved plan
- ActualCurrent evidenceComplete, active, blocked, and remaining work.
- VariancePlan comparisonCause, magnitude, affected milestone, and scope.
- ForecastRange + assumptionRemaining logic, capacity, risk, and review point.
- ActionOwner + decisionCorrective option, authority, date, and follow-up.
Status integrityNever move the baseline or hide a blocker merely to preserve a favorable label.
A useful status connects current work states and variance to forecast impact, action, and decisions.