Base status on evidence

A percentage-complete claim without a defined basis is weaker than milestone, acceptance, remaining-work, and blocker evidence.

Evidence-based status dashboard

Compare actual evidence with the approved plan

  1. ActualCurrent evidenceComplete, active, blocked, and remaining work.
  2. VariancePlan comparisonCause, magnitude, affected milestone, and scope.
  3. ForecastRange + assumptionRemaining logic, capacity, risk, and review point.
  4. ActionOwner + decisionCorrective option, authority, date, and follow-up.
Status integrityNever move the baseline or hide a blocker merely to preserve a favorable label.

A useful status connects current work states and variance to forecast impact, action, and decisions.

Choose True or False