Surface a missing dependency

A translation task is dated before source copy approval but no dependency is recorded. What should the coordinator do?

Deliverable breakdown map

Trace the outcome into owned, sequenced work

  1. OutcomeUseful changeThe result the project intends to support.
  2. DeliverableVerifiable resultA result with supplied acceptance evidence.
  3. Work packageManageable scopeOwned work that can be estimated and checked.
  4. DependencyPredecessor linkThe condition required before successor work proceeds.
Plan auditNo authorized deliverable is missing, unowned, or disconnected from its required predecessor.

Each planning layer should add enough detail to estimate, assign, sequence, and verify the authorized result.

Choose one answer