Free practice · ordering · hard

Practice

Move from defect to acceptance

Order the controlled path from a failed criterion to acceptance.

Quality and acceptance gate

Make readiness an evidence-based decision

  1. CriteriaObservable resultCondition, method, expected result, and reviewer.
  2. TestVersioned evidenceActual result, source, date, and exception.
  3. ResolveDisposition + retestSeverity, owner, action, and current status.
  4. AcceptAuthorized decisionReadiness, open conditions, owner, and record.
Delivery boundarySent is not accepted; required evidence and accountable approval remain visible.

Testable criteria connect prevention and review to defect handling, retest, and authorized acceptance.

Arrange in the correct order
  1. 1. Update readiness and record the acceptance decision
  2. 2. Correct or otherwise resolve, then retest
  3. 3. Assign owner and obtain authorized disposition
  4. 4. Record failed condition, evidence, impact, and version