Calculate simple risk exposure

A risk has a 25% probability and an estimated impact of 20,000. What is its simple expected exposure?

Scope and RAID control board

Keep boundaries, uncertainty, active issues, and changes distinct

  1. ScopeIn + outDeliverables, exclusions, constraints, and acceptance.
  2. RAIDClassifyRisk, assumption, issue, and dependency evidence.
  3. ResponseOwner + triggerPriority, action, due date, and escalation.
  4. ChangeImpact + decisionOptions, authorization, version, and communication.
Baseline controlAssess and authorize a change before altering committed scope, dates, or resources.

Each record has a different trigger, response, owner, and effect on the approved baseline.