Calculate simple risk exposure
A risk has a 25% probability and an estimated impact of 20,000. What is its simple expected exposure?
Scope and RAID control board
Keep boundaries, uncertainty, active issues, and changes distinct
- ScopeIn + outDeliverables, exclusions, constraints, and acceptance.
- RAIDClassifyRisk, assumption, issue, and dependency evidence.
- ResponseOwner + triggerPriority, action, due date, and escalation.
- ChangeImpact + decisionOptions, authorization, version, and communication.
Baseline controlAssess and authorize a change before altering committed scope, dates, or resources.
Each record has a different trigger, response, owner, and effect on the approved baseline.