Respond to an active issue

Order the response to a newly confirmed project issue.

Scope and RAID control board

Keep boundaries, uncertainty, active issues, and changes distinct

  1. ScopeIn + outDeliverables, exclusions, constraints, and acceptance.
  2. RAIDClassifyRisk, assumption, issue, and dependency evidence.
  3. ResponseOwner + triggerPriority, action, due date, and escalation.
  4. ChangeImpact + decisionOptions, authorization, version, and communication.
Baseline controlAssess and authorize a change before altering committed scope, dates, or resources.

Each record has a different trigger, response, owner, and effect on the approved baseline.

Arrange in the correct order
  1. 1. Update impacts, forecast, and stakeholder record
  2. 2. Assign resolution owner, due date, and escalation
  3. 3. Take authorized containment action
  4. 4. Confirm the issue, time, evidence, and affected work