Handle an informal scope request

An executive asks in chat for an additional launch feature. What should the coordinator do first?

Scope and RAID control board

Keep boundaries, uncertainty, active issues, and changes distinct

  1. ScopeIn + outDeliverables, exclusions, constraints, and acceptance.
  2. RAIDClassifyRisk, assumption, issue, and dependency evidence.
  3. ResponseOwner + triggerPriority, action, due date, and escalation.
  4. ChangeImpact + decisionOptions, authorization, version, and communication.
Baseline controlAssess and authorize a change before altering committed scope, dates, or resources.

Each record has a different trigger, response, owner, and effect on the approved baseline.

Choose one answer