Build a basic schedule

Order the schedule-building workflow.

Schedule logic line

Turn work evidence into a reviewable forecast

  1. EstimateEffort + rangeSource, assumption, uncertainty, and refinement point.
  2. SequenceLogic networkPredecessors, successors, parallel paths, and blockers.
  3. CalendarCapacity + datesWorking time, availability, and fixed constraints.
  4. ForecastMilestones + rangeCurrent expectation while the baseline stays visible.
Forecast ruleWhen evidence is uncertain, disclose the range and next review instead of inventing precision.

Effort and range estimates become dates only after dependencies, calendars, capacity, and milestones are applied.

Arrange in the correct order
  1. 1. Place milestones and review the forecast
  2. 2. Apply working calendars and available capacity
  3. 3. Connect predecessor and successor logic
  4. 4. Estimate effort and ranges for defined work