Free practice · ordering · medium
Practice
Build a basic schedule
Order the schedule-building workflow.
Schedule logic line
Turn work evidence into a reviewable forecast
- EstimateEffort + rangeSource, assumption, uncertainty, and refinement point.
- SequenceLogic networkPredecessors, successors, parallel paths, and blockers.
- CalendarCapacity + datesWorking time, availability, and fixed constraints.
- ForecastMilestones + rangeCurrent expectation while the baseline stays visible.
Forecast ruleWhen evidence is uncertain, disclose the range and next review instead of inventing precision.
Effort and range estimates become dates only after dependencies, calendars, capacity, and milestones are applied.